Close

Greenfield Installation

New Cell House Equipment Installation

AME was contracted to performan all rigging and installation of various foreign built process machinery for the new cell house building used to extract zinc.  Machinery included precision installation of several machine rails up to 260ft long, installation of automated process cranes, anode straightening equipment, cathode stripping lines, large aluminum power buss bars, six cooling towers installed on the building roof, and numerous other machines.  AME also received and unpacked over 300 overseas shipments and maintained the site’s storage yards and warehouse.  Project Value = $3,800,000